Dear friends,Re: Labour cessIt may be understood that the cess is to be paid by the person who incurs the cost of construction. In case a contractor undertakes to do construction work for the government or local authority, etc., cess will be deducted from his bi...

Labour cess - who is responsible to deposit the cess contractor or builder?(27/Jun/2010)

Dear Colleague,As per the provisions of the Building and other Construction Workers' Welfare Cess Act 1996, the cess levied under sub-section (1) shall be collected from every employer in such manner and at such time, including deduction at source in relation to...

Labour cess - who is responsible to deposit the cess contractor or builder?(27/Jun/2010)

Dear Sir,Subject: Labour CessWe are working with M/s JP Associated Limited, Pryagraj Thermal Power Project, Bara, Allahabad. I want to inquire about the cess which is covered in Delhi, Haryana, and U.P. for labor welfare, i.e., 1% of the total bill value. I woul...

Labour cess - who is responsible to deposit the cess contractor or builder?(27/Jun/2010)

Good morning to all my seniors,I am working with a contractor (construction). We are working for various builders in NCR. I want to ask regarding cess which is covered in Delhi, Haryana & UP for labor welfare, i.e., 1% of the total bill value.I want to ask, who ...

Labour cess - who is responsible to deposit the cess contractor or builder?(27/Jun/2010)

Hi, My name is Pradeep Manda, and I work in a manufacturing company. Recently, we received a notice from the Labour Department regarding labour cess. We responded that we have already paid it, but they have included the cost of plant and machinery as well.Could ...

Dear All,I am working at a hotel as an HR Manager. The establishment took place in 2014-15, and it is located in the RICCO area, for which we obtained an NOC from RICCo. However, I have received a notice from the labor department regarding BOCW/CESS Taxes after ...

Understanding BOCW Cess Act: Employer Liability and Cess Payment Clarifications(25/Jan/2019)

Hi,I want to clarify that as per the Building and Other Construction Workers Welfare Cess Act of 1996, who will pay the 1% of the cess amount on the total contract value? Is it the employer or the contractor?

Understanding BOCW Cess Act: Employer Liability and Cess Payment Clarifications(25/Jan/2019)

Dear,The cess under the BOCW Cess Act, 1996 is to be collected from the employer. For the definition of the employer, you may refer to section 2(i) of the BOCW (RE&CS) Act, 1996.Regards,R.N. Khola

Understanding BOCW Cess Act: Employer Liability and Cess Payment Clarifications(25/Jan/2019)

Dear Syam_1230,According to me, Cess is payable by the Principal Employer. This is because:i. the assessment of cess is done on the basis of the total construction cost (excluding land cost and compensation paid/payable under WC).ii. the information to be furnis...

Understanding BOCW Cess Act: Employer Liability and Cess Payment Clarifications(25/Jan/2019)

As per the definition of an employer under section 2 (i) of the BOCW (RE&CS) Act, 1996, the term "employer" includes contractors concerning contract labor. Please clarify if we hire a contractor and that contractor hires a sub-contractor, whether the sub-contrac...